project nu-shed, foundational edition (gravel dump one)

Since yesterday, we’ve transported and spread the first three cubic yards of gravel (No. 57 limestone; I've no clue what the other 56 varietals are like), with another three cubic scheduled for delivery tomorrow. Underestimated how much of a hill we had to build up. Not bad for it being less than three weeks since the first slices of demolition with a little more than three weeks to go until NuShed's arrival.

NuShed frame surrounding dirt.
NuShed frame surrounding dirt but with some gravel